The house takes months. Your rate lock doesn't. Buying a home that isn't built yet.

· Mandy Longshore, RE/MAX of Gulf Shores

A lot of the new-construction contracts getting written this month won’t close until spring. That’s normal. You pick a lot in a new community off the Foley Beach Express or up the Hwy 59 corridor, you pick a floor plan, and the builder starts.

What catches people is that the house and the mortgage run on two different clocks. The builder’s clock is measured in months. Your rate lock is measured in days. Get those lined up before you sign, not after the slab is poured.

How long the house actually takes

Per the Census Bureau’s Survey of Construction, a single-family home built for sale in the South took an average of 5.5 months from start to completion in 2025. A house a contractor builds on your own lot averaged 9 months.

Those are averages, and they start when construction starts, not when you sign. Permitting, a backlog of homes ahead of yours, weather and a busy inspection calendar all add time. Ask the builder two questions in writing: when do you expect to start my house, and what does the contract say happens if it runs late?

Where the rate lock fits

A rate lock holds your interest rate between the offer and closing. Per the Consumer Financial Protection Bureau, locks are typically available for 30, 45 or 60 days, and sometimes longer. The CFPB also says plainly that extending one can be expensive.

So on a house that’s five or six months from done, you have three honest options:

  • Float, then lock near the end. You take the rate that exists when the house is close to finished. If rates fall, you win. If they rise, you pay it.
  • Pay for a longer lock. Some lenders offer extended locks on new construction for an upfront fee or a slightly higher rate. Get the fee and the length in writing.
  • Take a builder’s lender offer. Many builders work with a preferred lender who can extend a lock or cover part of the cost. That can be a real benefit. It’s still an offer to compare, not a requirement to accept.

What a half point does

Here’s the math on why this matters. Freddie Mac’s weekly survey had the 30-year fixed at 7.18 percent on November 5.

Take a $399,200 loan, which is a $499,000 house with 20 percent down. At 7.18 percent, principal and interest come to about $2,704 a month. If the rate is half a point higher when you finally lock, that’s about $2,841. Half a point lower, about $2,571.

That’s roughly $135 a month either way, or about $1,600 a year, on the same house. Nobody can tell you which way it goes in five months. The point is to decide in advance how much of that swing you’re willing to carry, instead of finding out at closing.

A locked rate can still move

This is the part buyers don’t expect. The CFPB lists the common reasons a locked rate changes anyway: you change the loan type or your down payment, the appraisal comes in different than expected, your credit score changes, or the lender can’t document part of your income.

On a long build, that list is a warning. Months of waiting is a long time to keep your finances still. Don’t open a new credit card for the furniture. Don’t finance a truck. Don’t change jobs without calling your lender first. Pay every bill on time until the keys are in your hand.

Read the deposit before you sign

New construction usually asks for more money upfront than a resale. There’s earnest money, and there may be a separate deposit for upgrades and selections once you leave the design center.

Find out exactly which of those dollars are refundable and under what conditions. Ask what happens if your financing falls through, and whether the contract has a financing contingency at all. Selection deposits are often the least refundable money in the deal, so make your choices knowing that.

Compare the builder’s lender in writing

If the builder’s lender is offering an incentive, ask for it in writing. Then get a Loan Estimate from at least one other lender for the same loan.

The top of page 1 of every Loan Estimate shows whether the rate is locked and until when. Put the two side by side. Compare the rate, the lock length, the closing costs and the incentive together, because a big credit with a higher rate is not always the better deal over the life of the loan.

Before you sign a to-be-built contract

  • Get the builder’s expected start date and the late-completion terms in writing.
  • Ask your lender how long they’ll lock and what an extension costs.
  • Run the monthly at today’s rate and at half a point higher.
  • Find out which deposits are refundable, and when.
  • Get a second Loan Estimate if you’re offered a builder’s lender incentive.
  • Keep your credit and your job steady until closing.

None of this is a reason to skip new construction. A brand-new house is a good way to come home to the coast, and buying one in a slower winter can give you room to ask for terms. It just goes better when the mortgage plan is as specific as the floor plan.

If you’re looking at a build and want help lining up the dates and the numbers, call or text me at (251) 597-5809. No pressure, just honest numbers. I answer my phone.